|
Duct Bank Laying
When defining the path, the program connects selected nodal elements
using shortest possible path along the route (procedure 1). A precondition for duct bank laying is to have the trench routes and
manholes placed in the site plan. Duct bank laying command can be run in three ways:
|
Note: |
The following text describes the laying of duct bank using Duct bank (designed) command. The laying procedure is the same for all three commands. The only difference is in the properties that the laid duct bank will have in the end. These properties can be seen in the Properties window. Properties can be, for example, the number of ducts, duct type, year built etc. |
From the main menu run Conduit > Duct Ban
(designed) command.
The command is now active. The cursor is displayed as a small square with the text next to it instructing you to Select nodal infrastructure element. Select the nodal element by clicking on the manhole symbol (or its label). Red rectangle appears signaling that you have properly selected the nodal element (Figure 1).
Figure 1
Now click again on the next manhole symbol to select the next nodal element (manhole).
After selecting the second nodal element, second red rectangle is displayed, connected by a red line with the previous one. Red lines and rectangles are temporary and are displayed while in command (command is active). They represent the path of the future duct bank that’s being laid (Figure 2).
Figure 2
End the command by right-clicking or pressing the ENTER key.
The program automatically draws the duct bank along the assigned path.
Duct bank with its label appears in the site plan (Figure 3).
The duct bank is located at its default layer.
Line thickness and color are determined by the layer settings.
Figure 3
Note: |
In this example, we connect manhole MH1 and MH3 with
the duct bank , bypassing the MH2 manhole. |
From the main menu run Conduit > Duct Bank
(designed) command.
The command is now active. The cursor is displayed as a small square
with the
text next to it asking you to Select nodal infrastructure
element.
Select the nodal element by clicking on the manhole symbol (or its label).
Red rectangle appears signaling that you have properly selected the nodal
element (Figure 4).
Figure 4
The program expects you to indicate the next nodal element (Figure 5).
Figure 5
This requirement is always visible at the command line along with the additional
command option.
In this case, the additional option is run by pressing the letter T (Figure 6).
Figure 6
With one pressing of the letter T (or by
entering it in the command line) , you activate
additional command option and
you can now select the route-point with no objects (no manholes).
Click on the route-point to select it (Figure 7).
Figure 7
The second red rectangle is displayed, which is now connected by a red
line with the previous one.
Red lines and rectangles are temporary and are displayed while in command
(command is active).
They represent a path section of the future duct bank that’s being laid
(Figure 8).
Figure 8
Again, by pressing the letter T, you enable the selection of the next route-point (Figure 9).
Note: |
At this point you could immediately select manhole MH3,
as the path from the previously selected nodal element to the
manhole is the shortest possible, so the cable would pass that
way. |
Figure 9
The third red rectangle is displayed, which is now connected by a red line with the previous one. (Figure 10)
Figure 10
Now you can select the last nodal element of the route.
This time you select the manhole symbol, so there is no need to run additional
command options.
Figure 11
The entire path of the future duct bank is drawn with a red line.
End the command by right-clicking (or pressing the ENTER key).
Duct bank with the corresponding label is generated along the path (Figure
12).
Figure 12
Additional information on the principles of linear infrastructure laying
in TeleCAD-GIS
are on Laying Linear
Infrastructure page.